Installment preparation work of the concrete mixer
Jun 29, 2017
Generally, no matter for stationary,moblie type or the demolition-mixing plant , there is the installment problem, but the installment work of the mobile mixing plant equipment is easy, and the work of the fixed
concrete mixer is pretty large. Before the installment, the technology data shall be prepared, and the power, gas source and water source shall be ready, preparing for the installment of the device. The installment shall strictly follow the steps provided by the machine supplier, at the same time, it shall follow the operation regulation of the machine and electronic installment, when installing, the hot temperature equipment shall be taken into consideration, because it will have big influence on the quality and performance of the concrete.
The following things need to be done before the operation of the new machine: first, check if all the ground screw is tightly fixed and connection status of the electric lines. Check if there is the foreign odds in the
concrete mixer. Check the safety of the crane and the transportation components as well as the ladder, finally check the reliability of the urgent stop device and the unblocking of the emergency exit. The Haomei Machinery Co., Ltd has 30 years experiences in manufacturing the concrete mixer, and it will send the professional consultant to supervise the installment of the concrete mixer to ensure that the clients will be satisfied with the service, and if you have any demand for the concrete mixer, please contact us, and we will give you the best recommend!