In the commercial concrete batching plants, the feeding method basically adopts the belt conveyor type. In the small-scale concrete batching plant, the the skip hopper feeding method is usually adopted. The feeding speed of the belt conveyor is fast, and the working performance is stable. However, the installation is rather cumbersome and requires professional installation personnel. Usually, the
belt conveyor type concrete batching plant suppliers provide installation service of the belt conveyor by engineers with rich experience.
1, Check the components of the belt type concrete batching plant equipment. Since the concrete mixing plant equipment is transported by dispersion, many parts are separated and not assembled together. Therefore, when the
belt conveyor type concrete batching plant is pulled to the site, the equipment must be inventoried,check whether the quantity is correct, the equipment has damage and integrity, etc.
2, The belt conveyor is assembled on the ground. The bridge legs and the truss are bolted, and the mechanical components such as the roller set and the conveyor belt are assembled on the truss.
3, Hoisting the belt conveyor. When hoisting, ensure that the truss spans 50mm. The lifting truss and the belt conveyor head frame are firmly connected, and the legs are connected with the foundation. The hoisting tail beam is coupled to the tail conveyor of the belt conveyor. Mechanical components such as cleaners are assembled on the truss. Finally, adjust the mechanical parts of the belt conveyor, and fix the belt cover rain cover after fixing.
4, Install the belt conveyor roller set. When loading each roller set and the redirecting roller in the rack, check that the axes are parallel to each other and in a straight line, and whether they are perpendicular to the center line of the truss. The bolts of the steel structure must be properly matched according to the design drawings, especially when high-strength bolts are used, and ordinary bolts should not be used instead.
5, Finally install the belt conveyor. When installing the belt conveyor, first adjust the reversing roller to the front, make the belt tensioned properly, and the joint should be firmly adhered.
6, Inspection work by
belt conveyor type concrete batching plant suppliers after installation. During the storage, the components should be properly maintained. After the installation is completed, paint should be applied on the components.