Customers ordering concrete batching plant, we need to in situ measurements, how to arrange plant placed, Foundation design manufacturers are responsible for surveying, design, diagram, below, to learn more about us:
1, concrete mixing station based on level must be level and flat instrument, if not responsible for losses due to underlying inequalities.
2, prepare embedded iron as required, according to the batch plant drawings, embedded iron size shall not be altered arbitrarily, if need to change venue technical staff must be informed, make written proof;
3, concrete mixing station based on laying mesh reinforcement, steel anchor hooks are drawings shall not be less than the requested size; infrastructure needed to dig depth and width shall not be less than required dimensions in drawings;
4, shall not be altered arbitrarily drawing dimensions that are marked, such as changes to inform the venue technical staff, written proof;
5, according to the technical requirements of self loading batching plant on line, finding a good reference point, between the two basic dimensions not larger than 50mm, lime sub centres based on the location and the size of the mining base scope;
6, after passing the basic mining pouring concrete, take second cast have second cast, labels can be as C20-C30;
7, digging foundations, steel or wood chunks set aside the underlying position of the Center, clear labelling requirements, the same basic position of the two embedded iron Center to be on the same line, the deviation shall not be greater than 20mm;
8, embedded iron before pouring is completed must be maintained when placing above and horizon ± 0.00 level and parallel to the adjacent embedded iron levels, and without twist, off center